View Full Version : Changing multiple views at once (carried over from the Wishlist)



gregcashen
2004-09-09, 07:29 PM
...for changing multiple views at once: you can create a view schedule. It will list all the views within your project. Then, on the grouping tab, you can set the options so that it doesn't itemize every instance, and so that it groups all the views you want to change (like all elevations that start with a certain letter or something) into a single line on the schedule. Then you can simply change the scale within the schedule, and all those views will change too...

This goes straight to the top of my favorite tips and tricks. Thanks Jeffrey!

hand471037
2004-09-09, 08:27 PM
It's not just for views. within every job I'll have several 'working schedules'. These schedules never get put onto sheets, and are only there as a fast global editing aid. Just by changing the grouping options you can single out the things you want to change, and then change them all at once. It's also great for quick counts and totals.

Combine this with Key Schedules, and you can really start to rock. :D

Cathy Hadley
2004-09-10, 12:02 AM
Okay... I'm missing something easy...

How do you create a view schedule?

CZH

irwin
2004-09-10, 12:21 AM
Okay... I'm missing something easy...

How do you create a view schedule?

CZH

View | New | View List...