    Question Concrete Beam Schedules

    We're still using ACAD on old projects, but using RST on new projects. Luckily the new ones have been steel. However, I know the day is coming where I need to model a concrete structure in RST.

    How are you handling Concrete Beam Schedules? When using ACAD, we're typing all the information into Excel spreadsheets. Then, we use a 3rd party program to import the XLS ranges into ACAD. Once set up, the 3rd party program is a snap when we need to update the spreadsheets in ACAD. (I'm attaching an example of a small portion of our beam schedule)

    I cannot see how I'm going to handle this in the future when we get our first Concrete building in RST.

    What are you doing?
    Attached Images Attached Images

  2. #2
    Super Moderator david_peterson's Avatar
    Join Date
    2002-09
    Location
    Madison, WI
    Posts
    5,687
    Login to Give a bone
    0

    Default Re: Concrete Beam Schedules

    We've added parameters to the concrete beams and let them drive the schedule.
    The schedule refers to a legend that shows all the different bar configurations.
    I model all the beams and let my engineer fill out the schedule in Revit.
    Working great so far.

  3. #3
    Director of Operations David Harrington's Avatar
    Join Date
    2000-10
    Location
    Tampa, Florida
    Posts
    416
    Login to Give a bone
    0

    Default Re: Concrete Beam Schedules

    I agree with the other Dave, works great...generally.

    About the biggest hassle is that beams don't show up in the schedule until they exist in the model. So sometimes I'll do a large array of beams to build that initial schedule, then it can be filled out in any number of methods.

    The other challenge is what happens when a given beam type is removed from the plan, it drops from the schedule too. This is often not desirable, rather a NOT USED put on that row in the schedule. Sometimes to solve that I'll make a beam graveyard off the project area where the beam can sit and therefore populate the schedule.
    Take care,
    David Harrington
    AUGI Director of Operations

  4. #4
    Super Moderator david_peterson's Avatar
    Join Date
    2002-09
    Location
    Madison, WI
    Posts
    5,687
    Login to Give a bone
    0

    Default Re: Concrete Beam Schedules

    Well for me Since I have to model them anyway, we pick out out typ beam width an depth for the project (24x24) and frame out the building using 1 beam type. Next I go around and duplicate each beam and give each beam it's own unique beam number (type) like 2B137. Then I'll go to the schedule and apply a manufacturer parameter (based on what level I want to call the beam schedule (ie canopy beam schedule) so I can filter them out.
    I haven't seen what the fabricator has sent back for shops yet, but they haven't called or sent an RFI so I'm hoping they understand it.

  5. #5
    Member
    Join Date
    2004-05
    Location
    Los Angeles
    Posts
    4
    Login to Give a bone
    0

    Default Re: Concrete Beam Schedules

    I learnt that if the rebar parameters is added to the family definition then it can be exported and modified in Excel and back imported. whereas if it is added as instance parameter then it can only be exported. The issue with family parameters is we will end up with so many unique beam types. What is the workaround? I am not sure if this could be handled by scripting and tapping the API objects.

  6. #6
    Director of Operations David Harrington's Avatar
    Join Date
    2000-10
    Location
    Tampa, Florida
    Posts
    416
    Login to Give a bone
    0

    Default Re: Concrete Beam Schedules

    Everyone I know, and including my firm, ends up with many beam types (1 type per mark on plan). It is the best to deal with the task at hand.
    Take care,
    David Harrington
    AUGI Director of Operations

Similar Threads

  1. 2013: Concrete Slab/Concrete Beam Join
    By lowm445034 in forum Revit Structure - General
    Replies: 1
    Last Post: 2013-11-21, 03:59 PM
  2. 2012: Concrete Beam Won't Join Concrete Roof Slab at Ridge..HELP
    By tedg in forum Revit Structure - General
    Replies: 8
    Last Post: 2012-10-15, 07:15 PM
  3. Replies: 1
    Last Post: 2010-08-30, 05:46 AM
  4. How to cut a concrete beam?
    By stephanschneller in forum Revit Architecture - General
    Replies: 5
    Last Post: 2010-06-09, 12:50 PM
  5. Concrete beam with sloped top + Beam family question...
    By scowsert in forum Revit Structure - General
    Replies: 0
    Last Post: 2007-12-22, 03:36 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •