My question: How do we select(attach) items(materials) by each floor instead of linking(Attaching) every single items to time liner?
I have a 4 stories building which has Structure and MEP together.
I am going to make a construction process video with my Navisworks.
After importing my Revit files(combined files- MEP and Arch.), I try to select items by floor.
e.g. when I try to select all diffusers on the 1st floor, I couldn't select the diffusers on the 1st floor. I'm only able to choose either all of the diffusers for entire building or one item at a time. I wish I could choose all diffusers on the 1st floor only at a time, and attach it to the 1st floor air terminal schedule. And then go to 2nd floor to attach the diffusers on the 2nd floor to the lime liner.
Is there any way that I could choose/attach the same category items by each floor(level)?? If not, it will take forever.......
Thanks in advance.