    One of our consultants is new to Revit, so new that 2012 is the first and only version they have. For this project, we are still in 2011.

    We were sent a 2012 file. I loaded it in 2012 and looked in vain for a 'save as 2011'.

    Is there a way to convert?, or, is the file format interchangeable? or, am I outta luck?

  2. #2
    Super Moderator david_peterson's Avatar
    Join Date
    2002-09
    Location
    Madison, WI
    Posts
    5,687
    Login to Give a bone
    0

    Default Re: convert 2012 to 2011?

    Nope, you are out of luck.
    Revit was and always will be unable to go backwards. ie not backwards compatible.
    You're SOL. The only thing you can do is have them export to cad and try to use that as a back ground for your plans.
    Or you could upgrade to 2012.

  3. #3
    AUGI Addict
    Join Date
    2015-11
    Location
    Madison, WI
    Posts
    1,318
    Login to Give a bone
    0

    Default Re: convert 2012 to 2011?

    Mike,

    Is there a client/consultant requirement for it to be in 2011? Who is the lead (contract holder) for your project? What is in the contract for required deliverables? Are you not on subscription?

    Jeff S.

  4. #4
    AUGI Addict MikeJarosz's Avatar
    Join Date
    2015-10
    Location
    New York NY
    Posts
    1,497
    Login to Give a bone
    0

    Default Re: convert 2012 to 2011?

    The consultant is new to a project that's been on and off for almost two years now. That's how it got started in 2011. We are on subscription and I pointed out that I did load it into 2012. However, we are not the lead Architect and the lead architect wants 2011.

    I know about the Penn State BIM Execution Plan, and we are creating one for a very big project we are just starting up, but this project is small and the lead architect didn't create one.

  5. #5
    AUGI Addict
    Join Date
    2015-11
    Location
    Madison, WI
    Posts
    1,318
    Login to Give a bone
    0

    Default Re: convert 2012 to 2011?

    Okay, so who holds the contract with this consultant? Is it your firm or the lead Architect? In the sub-contractor's contract, does it spell out what software they're required to use? This is something that we're trying to alert to management. If we hold the contract, we need to decide what software consultants are required to provide to us.

    Cheers,
    Jeff S.

  6. #6
    Mod / Salary / SM Wanderer's Avatar
    Join Date
    2001-12
    Location
    St. Louis
    Posts
    5,406
    Login to Give a bone
    0

    Default Re: convert 2012 to 2011?

    Quote Originally Posted by jsteinhauer View Post
    Okay, so who holds the contract with this consultant? Is it your firm or the lead Architect? In the sub-contractor's contract, does it spell out what software they're required to use? This is something that we're trying to alert to management. If we hold the contract, we need to decide what software consultants are required to provide to us.

    Cheers,
    Jeff S.
    ~nodding~ That is one thing in our (client side) contract requirements. I don't dictate who on each project is 'in charge of' or ultimately responsible for the turnover of the design documents, because that can vary by project (sometimes archie, sometimes gc, sometime engineer, depending on scope and team). But, I do specify that, when the team is using BIM, version is to be jointly determined at the start of the project, and put down in writing, no upgrades to take place to the model without written consent of all working on it.
    Melanie Stone
    @MistresDorkness

    Archibus, FMS/FMInteract and AutoCAD Expert (I use BricsCAD, Revit, Tandem, and Planon, too)
    Technical Editor
    not all those who wander are lost

Similar Threads

  1. .NWC Export 2011 & 2012
    By chris4455 in forum NavisWorks - General
    Replies: 0
    Last Post: 2011-12-28, 11:39 PM
  2. Revit MEP 2011 to 2012
    By scraven in forum Revit MEP - General
    Replies: 3
    Last Post: 2011-10-28, 03:18 PM
  3. Going from 2011 to 2012
    By jspartz in forum NavisWorks - General
    Replies: 6
    Last Post: 2011-09-21, 10:55 AM
  4. Conditional Formatting in 2011 or 2012
    By silexz in forum Revit Architecture - General
    Replies: 4
    Last Post: 2011-07-20, 06:41 PM
  5. convert displacement map?? in 3ds max design 2011
    By vorschau275365 in forum 3ds Max - General
    Replies: 3
    Last Post: 2011-04-04, 05:02 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •