    Hi,

    I have a problem with finding curtain walls with the find tool. i made in Revit a shared parameter named task id's. I named my curtain walls into 001 for V1 and 002 for V2. But i can't find 001 and 002 because they are curtain walls. i can't select the walls, only the panels and mullions. know someone how i find the walls on another way?

    Thanks

  2. #2
    All AUGI, all the time pauljordan's Avatar
    Join Date
    2004-09
    Location
    Rock -- Me -- Hard Place
    Posts
    721

    Default Re: Revit / Navisworks manage task id and sets problem

    Quote Originally Posted by herwin_240279 View Post
    Hi,

    I have a problem with finding curtain walls with the find tool. i made in Revit a shared parameter named task id's. I named my curtain walls into 001 for V1 and 002 for V2. But i can't find 001 and 002 because they are curtain walls. i can't select the walls, only the panels and mullions. know someone how i find the walls on another way?

    Thanks
    If you can post a copy of an .nwd file, we might be able to help you find what you're looking for. Personally, I would probably work with the selection sets and create a set for them. Then use that to find the walls.
    Give a man AutoCad, and he'll draw you a floor plan.
    Give a man Revit and he'll build you a house.
    Give Cadmama a couple of drinks and she'll have everyone singing Rockytop!

  3. #3
    100 Club mitch.cornelius's Avatar
    Join Date
    2008-05
    Location
    Salt Lake City, UT
    Posts
    171

    Default Re: Revit / Navisworks manage task id and sets problem

    As far as I know you can't view the curtain wall objects from Revit on their own - the geometry of the curtain wall is found in its mullions and panels. You may need to assign the shared parameter for task ids to the panels and mullions to make your workflow work.

Similar Threads

  1. Problem with Navisworks manage
    By igor.bergonzoni285578 in forum BIM Management - General
    Replies: 0
    Last Post: 2011-12-11, 09:10 AM
  2. NW Manage 2010 - Unable to export Search Sets XML
    By dderoeck in forum NavisWorks - General
    Replies: 7
    Last Post: 2010-08-27, 04:13 PM
  3. Revit Files to Navisworks Manage
    By adidier in forum NavisWorks - General
    Replies: 4
    Last Post: 2010-01-26, 09:24 PM
  4. navisworks V5 to manage 2010
    By matt.schnoor in forum NavisWorks - General
    Replies: 0
    Last Post: 2009-05-28, 12:25 PM
  5. Revit MEP 09 and Navisworks Manage
    By yuen_kevin in forum NavisWorks - General
    Replies: 1
    Last Post: 2008-11-30, 01:11 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •