A hypothetical question for you Reviteers: Let's say you have a nice foundation with spread footings, stemwalls, and some wonderful building above. A large truck is going to come in and dump gravel that will fill in the bottom of excavation, in between all the footings (including those isolated column footings that keep changing size), then cover the tops of footings and go a foot or so up the stemwalls/pedestals etc. A slab will go above the fill. The bottom of slab has a different slope than the bottom of your excavation (pad anyone?), because you always scrape the bottom of excavation level, but the slab is sloped, so the fill has varying thickness.
How would you model that in the wonderful world of BIM? Would you bother? Would you just use filled regions on the sections? Hoping to learn something here...