    Default Revit MEP 2013 Phasing

    Good Morning Everyone,

    I have a few quick questions about phasing in Revit MEP 2013. I have just recently started to use revit MEP 2013 ( we got building design suite premium for 4 years ) I am pretty familiar with the revit as a software ( previous came from a position were we designed baggage handling systems for airports, and we used revit architecture 2012, 2011 to accomplish this.) @ my previous position using the phasing feature was great when doing small airport upgrades or improvements. My question is how do you go about using the phasing in MEP? I have been working on a small job that is an overall building improvement / upgrade and we will be tying into a majority of the existing HVAC / Plumbing & Electrical. I have noticed that once you set a string of duct work and a AHU to existing phase and to be demoed in the appropriate phase the system is now undefined and i can not change this. What would be the correct way of showing phasing in MEP models.

    Thanks
    Josh

  2. #2
    I could stop if I wanted to
    Join Date
    2015-11
    Location
    Saint Louis, MO
    Posts
    484
    Login to Give a bone
    0

    Default Re: Revit MEP 2013 Phasing

    not that it's entirely correct, but do you need to worry about whether the system being demo'd is an actual system, or connected properly?

  3. #3
    Member
    Join Date
    2016-01
    Location
    Rocky Hill, CT
    Posts
    13
    Login to Give a bone
    0

    Default Re: Revit MEP 2013 Phasing

    Mhartmann,

    it would be nice if the systems stay connected properly.

  4. #4
    Member
    Join Date
    2009-02
    Posts
    39
    Login to Give a bone
    0

    Default Re: Revit MEP 2013 Phasing

    Once you demo the duct work it becomes disconnected and no longer retains a system type. It virtually becomes a dumb section of disconnected duct work.

  5. #5
    I could stop if I wanted to
    Join Date
    2011-01
    Posts
    226
    Login to Give a bone
    0

    Default Re: Revit MEP 2013 Phasing

    We're going through the second phase of a large project now where a significant amount of MEP content is being demolished. The problem with duct (or pipe) losing its connectivity after being demolished is that its visibility can no longer be controlled by view filters specific to system type. And because the elements are not connected Revit will try to break linework when the view type if set to Mechanical. Very irritating.

    To solve the first problem you can use a separate workset for demolished ductwork. Then you can control its visibility. For piping this is essential, because once demolished there is no longer any difference between plumbing pipes and mechanical pipes. So they show up on each other's sheets. Again, an extra workset for each does the trick. If that messes up your workset structure you can add a text based project parameter that you could fill in with PLUM, MECH, etc. and set up a view filter to turn things on or off that way.

    Hope it helps.

  6. #6
    Member
    Join Date
    2016-01
    Location
    Rocky Hill, CT
    Posts
    13
    Login to Give a bone
    0

    Default Re: Revit MEP 2013 Phasing

    Neightyeight,

    Thanks for the suggestion of using worksets. I had thought about this but was unsure. Started to show my demo with someone of the existing system. Still using the phase created as "existing" and phase demolished "new construction" placed on a new the new demo workset and seems to function the way i need it to. d1.JPG

  7. #7
    I could stop if I wanted to
    Join Date
    2011-01
    Posts
    226
    Login to Give a bone
    0

    Default Re: Revit MEP 2013 Phasing

    Glad it helped.

Similar Threads

  1. Exportar Revit 2012-2013 a 3ds Max Design 2013...
    By magdagarciavinuesa in forum Revit Architecture - General
    Replies: 2
    Last Post: 2015-02-04, 10:34 PM
  2. 2013 Objects From Revit MEP 2013 Missing in Navis Manage 2013
    By MetalliCAD in forum NavisWorks - General
    Replies: 5
    Last Post: 2013-03-05, 08:52 PM
  3. Revit 2013 Detail Views Showing up in Navisworks 2013
    By tfullerpipes in forum NavisWorks - General
    Replies: 3
    Last Post: 2013-01-30, 07:37 AM
  4. 2013 Revit 2013 to navisworks Manage 2013
    By markclarenzze in forum NavisWorks - General
    Replies: 9
    Last Post: 2013-01-14, 10:02 AM
  5. Revit DB Link 2013 and Access 2013?
    By KELLI in forum Revit Architecture - General
    Replies: 0
    Last Post: 2012-11-20, 04:29 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •