Originally Posted by
mhartmann
I would use 2 separate panels, maybe stacked on a wall so they'll show as one in plan. if your emergency panel is sub-fed from a breaker in the normal panel, then you'll be able to get total emergency load and total combined loads, they will go thru to the bus of the normal panel via the 3-pole breaker. you will have 2 separate panel schedules, but your math would be correct. I think you'll have to fake and size yourself the emergency feeder to the generator for your plans/one-line. revit won't care at that point.
hth,
mike