at our local construction site we have a problem, The second floor of a residential project is poured 60mm to high. the level should have been +4600 but now it will be +4660 the problem is that the doors will not fit because the door lintels are also in place, i Know this is not really a question for this forum, but i think you guys know a lot about the construction business and maybe someone has a better solution, the only solution we have right now is to put in shorter doors, please let me know if someone has a better solution for us,

Thanks!