    Default Architectural model is set above 0'-0" so the copy/monitored levels don't match the Arch levels

    Hi All,

    I am setting up a new structural project and when I linked in the arch model I found that Level 01 in the arch model is at 96'-0". So when I started copy/monitor for the levels, they didn't match.


    Here is what I though of:
    1. I though of simply relocating the project, which fixed the problem, but I am sure if this a correct approach.
    2. I tried acquiring the coordinates from the arch model but nothing changed.


    Please advice, what is the best practice to fix this issue?

    Thanks a lot.

  2. #2
    Certifiable AUGI Addict dhurtubise's Avatar
    Join Date
    2005-07
    Location
    Somewhere in the BIM world
    Posts
    3,792
    Login to Give a bone
    0

    Default Re: Architectural model is set above 0'-0" so the copy/monitored levels don't match the Arch levels

    Did you check if the arch model is using Project Base Point to Display 96'?
    If so, no shared coordinates are involve so just relocate your project.

  3. #3
    Member
    Join Date
    2012-08
    Posts
    13
    Login to Give a bone
    0

    Default Re: Architectural model is set above 0'-0" so the copy/monitored levels don't match the Arch levels

    Quote Originally Posted by dhurtubise View Post
    Did you check if the arch model is using Project Base Point to Display 96'?
    If so, no shared coordinates are involve so just relocate your project.
    Yes you are right, the architectural base point is showing 96'-0".
    Can you please explain the other case? what if he didn't relocate his model?

  4. #4
    Certifiable AUGI Addict dhurtubise's Avatar
    Join Date
    2005-07
    Location
    Somewhere in the BIM world
    Posts
    3,792
    Login to Give a bone
    0

    Default Re: Architectural model is set above 0'-0" so the copy/monitored levels don't match the Arch levels

    You would then use Shared Coordinates. Shared would display site elevation(96') and project would display 0'

Similar Threads

  1. 2013: Levels in linked arch model changed. Now what?
    By stevedav453315 in forum Revit MEP - General
    Replies: 2
    Last Post: 2014-03-20, 07:56 PM
  2. 2012: Importing Revit Arch model & levels
    By Damo in forum Revit MEP - General
    Replies: 7
    Last Post: 2012-03-07, 05:19 PM
  3. plans for Copy/Monitored levels
    By Bryan Thatcher in forum Revit Structure - General
    Replies: 1
    Last Post: 2009-01-13, 06:14 PM
  4. Replies: 1
    Last Post: 2008-11-03, 12:01 PM
  5. switching the sys. variable "Elev" to match project levels
    By jgardner.79905 in forum VBA/COM Interop
    Replies: 1
    Last Post: 2006-04-20, 08:55 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •