    Default Level Differences (Execution project Z values minus observed Z values)

    My name is Ribeiro and I work for the Portuguese Government developing inspection work in roadway building area.
    Before each pavement laying I usually perform a survey in order to verify the Z-levels used by the constructor.
    My question is:
    - Can I use 3D points randomly observed in the sub-pavement to establish differences in level (height) to the correspondent corridor COGO points (Civil 3D project points)?. Putting it in another way (at least trying to): I observe one point at a determined chainage and offset obtaining it's 3D coordinates. With the 2D values (X,Y) can I obtain the correspondent 'project' value and establish a difference to the observed one (supposing of course that I have my corridor builded...). What about if I have 100 observed points?

    Thankfully,
    P Ribeiro

    PS - Please let me know if I can post the same question in the Portuguese forum (maybe it is not a Civil 3D forum)

  2. #2
    Civil Engineering Moderator MHultgren's Avatar
    Join Date
    2000-12
    Location
    Indy West (Not West Indies)
    Posts
    1,446
    Login to Give a bone
    0

    Default Re: Level Differences (Execution project Z values minus observed Z values)

    Use your observed points as a seperate point group and you can import them into your corridor to find the elevation or depth from surface easily enough.

  3. #3
    Active Member
    Join Date
    2005-01
    Posts
    60
    Login to Give a bone
    0

    Default Re: Level Differences (Execution project Z values minus observed Z values)

    Take your design surface and use the observed points to build a surface from the survey observations. To compare them to each other;create a sample line group and plot the differences in section views.

Similar Threads

  1. Global project parameter values?
    By lmcgill2500924 in forum Revit MEP - General
    Replies: 1
    Last Post: 2012-03-20, 03:14 AM
  2. 2012: Spot elevation and level head show 2 different values
    By 1966ford in forum Revit Architecture - General
    Replies: 2
    Last Post: 2011-11-07, 09:54 PM
  3. Replies: 4
    Last Post: 2008-11-13, 05:36 AM
  4. Relocated Project conflit with Schedules with Calculated Level Values
    By rajan_receptive in forum Revit Architecture - General
    Replies: 4
    Last Post: 2007-11-27, 09:19 AM
  5. Default Project Parameter Values
    By mjdanowski in forum Revit MEP - Wish List
    Replies: 0
    Last Post: 2007-07-31, 08:26 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •