    I am thinking of creating finish plans instead of finish shedules. I could tag walls and materials in each room which would do essecially the same thing as a schedule and maybe be a little more bim like.

    What is everyone else doing? Any short falls with the plan method?

    Justin

  2. #2
    Active Member
    Join Date
    2005-12
    Location
    Atlanta, GA
    Posts
    95
    Login to Give a bone
    0

    Default Re: finish plans instead of finish schedules?

    We do both actually. We've found it's just easier to show our floor patterns in plan (including blow ups when we need them) as well as finish tags for the walls, base and floor. However for many rooms, the room itself is not big enough to fit all the tags in, so we use a finish schedule that has a column for each room, all four walls, and the rest of the finishes that apply to the room.

    My firm has a pretty sizeable interior design department though, so our finish plans are usually pretty busy. This wouldn't really apply to firms who don't do ID.

  3. #3
    All AUGI, all the time Justin Marchiel's Avatar
    Join Date
    2004-07
    Location
    Penticton, B.C., Canada
    Posts
    954
    Login to Give a bone
    0

    Default Re: finish plans instead of finish schedules?

    how are you tagging the finishes on the wall? Are you creating a finish parameter on the wall? what happens if there is a different finish on the other side of the wall? do you have a finish inside and finish outside parameter?

    I would like to have the finish information reside with the walls, but i can't see how to schedule the finish on the walls to relate to the room in which they occur.

    Could you shed a little more light on your process.

    Thanks

    Justin

  4. #4
    All AUGI, all the time
    Join Date
    2005-01
    Location
    Milwaukee, Wisconsin
    Posts
    636
    Login to Give a bone
    1

    Default Re: finish plans instead of finish schedules?

    Quote Originally Posted by jmarchiel-barch
    Any short falls with the plan method?
    You mean other than complaints about "we always did it with a schedule before" or "why are we changing this" or "I liked it better the old way?"

    We are using only finish plans. We created a tag that still draws it's information from the room that reflects only the floor, base, walls and remarks. If there is complex information like floor patterns or carpet border or multiple colors, the tag just has dashes and the information is indicated on the plan with keynotes.

    We found it too difficult to put the parameter in the wall and tag the material that way (for example) because then we would be forced to have individual sections of wall just because a paint color changed. But we thought about it before bagging the idea.

    Ceiling finishes are tagged on the reflected ceiling plan using actual ceilings. Laminate colors are indicated in the elevations as part of the casework family.

    Seems to be working so far - even made this work in some of our legacy ADT projects still on the boards using Spaces instead of Rooms. Perfect for our medical projects.
    Attached Images Attached Images

Similar Threads

  1. Room Finish Schedules
    By ebtrad in forum Revit Architecture - General
    Replies: 7
    Last Post: 2017-02-17, 07:22 PM
  2. 2013: Interior Finish Schedules and Finish Legends - best way to create?
    By jburdzinski383198 in forum Revit Architecture - General
    Replies: 1
    Last Post: 2013-05-22, 09:32 PM
  3. Plans showing only stud walls - no finish
    By Henry D in forum Revit Architecture - Tips & Tricks
    Replies: 9
    Last Post: 2011-06-28, 07:42 AM
  4. RAC 2010 - Best practices for Interiors - Finish Plans
    By designviz in forum Revit Architecture - General
    Replies: 10
    Last Post: 2009-12-29, 02:38 PM
  5. Automatic Finish schedules
    By jwilhelm in forum Revit Architecture - General
    Replies: 12
    Last Post: 2007-12-28, 05:39 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •