Thread: Door schedule issue

  1. #1
    Certifiable AUGI Addict dhurtubise's Avatar
    Join Date
    2005-07
    Location
    Somewhere in the BIM world
    Posts
    3,792
    Login to Give a bone
    0

    Default Door schedule issue

    We have a door schedule were we want to report From Room number and To Room number. I can insert the field but they don't populate. Actually no information from Room can be included. All fields shows blank.
    We do have a room schedule that shows all the information.
    Any ideas why ?

  2. #2
    All AUGI, all the time christo4robin's Avatar
    Join Date
    2003-05
    Location
    Boulder, Colorado
    Posts
    681
    Login to Give a bone
    0

    Default Re: Door schedule issue

    Daniel,

    I know this has been an issue for people in the past. You might search the forums a bit to see what you can find.

    Personally, I had this issue when the room object and the door object were not based on the same level (two floors 12" apart, rooms all created to be associated with the higher level, doors on the lower level did not populate the from room and to room fields.)

    Hope that helps.

  3. #3
    All AUGI, all the time Justin Marchiel's Avatar
    Join Date
    2004-07
    Location
    Penticton, B.C., Canada
    Posts
    954
    Login to Give a bone
    0

    Default Re: Door schedule issue

    just a word of caustion. the to from is not always acurate. i have noted it before that you can actually switch the to from in the schedule without the door actually flipping. been awhile since i said it, so i thought i might mention it again.

    Justin

  4. #4
    Revit Forum Manager Steve_Stafford's Avatar
    Join Date
    2001-12
    Location
    Irvine, CA
    Posts
    7,567
    Login to Give a bone
    0

    Default Re: Door schedule issue

    Not accurate...but on purpose. The direction the door swings does not always dictate the room the door belongs to. A door that must swing out of a classroom belongs to the classroom, not the corridor. If you want the TO value to represent what room the door belongs to then you need Revit to work the way it does. If you want the TO value to mean where the door literally swings in to then it doesn't.

    Daniel, any chance phases are involved? If your rooms are in a different phase they wouldn't show up in the schedule or if the door schedule itself is assigned the wrong phase. Sorting and Grouping settings can sometimes prevent them from displaying too.
    Last edited by Steve_Stafford; 2007-02-01 at 05:14 PM.

  5. #5
    Certifiable AUGI Addict dhurtubise's Avatar
    Join Date
    2005-07
    Location
    Somewhere in the BIM world
    Posts
    3,792
    Login to Give a bone
    0

    Default Re: Door schedule issue

    Steve it's all brand new construction so there is no phasing involve

Similar Threads

  1. 2012: Door Schedule Plotting Issue
    By tra1133 in forum ACA General
    Replies: 5
    Last Post: 2013-10-22, 01:01 PM
  2. 2012: Door Schedule Issue- Rogue Door Tag
    By tra1133 in forum ACA General
    Replies: 5
    Last Post: 2012-12-04, 06:09 PM
  3. door schedule issue....
    By ntnik in forum Revit Architecture - General
    Replies: 3
    Last Post: 2009-02-01, 08:28 PM
  4. strange door schedule issue (2007)
    By sharla in forum ACA General
    Replies: 1
    Last Post: 2006-07-31, 10:16 AM
  5. Door schedule/tag issue
    By BrettP in forum ACA General
    Replies: 14
    Last Post: 2006-07-10, 08:44 PM