    Default room finish schedule

    Is it possible to create a schedule like the one attached? I can't figure out how to create 4 separate columns for North/south/west/east walls. Thanks in advance!
    Attached Images Attached Images

  2. #2
    Certifiable AUGI Addict dhurtubise's Avatar
    Join Date
    2005-07
    Location
    Somewhere in the BIM world
    Posts
    3,792
    Login to Give a bone
    0

    Default Re: room finish schedule

    Use Shared Parameter for that purpose.

  3. #3
    Revit Mararishi aaronrumple's Avatar
    Join Date
    2002-02
    Location
    St. Louis, MO
    Posts
    4,695
    Login to Give a bone
    0

    Default Re: room finish schedule

    Actually there are several options.

    If it is just going to be in the schedule, I wouldn't use a shared parameter, but rather a project parameter.

    You might also conside using a schedule key if there will be a lot of typical data entry.

  4. #4
    Active Member
    Join Date
    2006-03
    Posts
    58
    Login to Give a bone
    0

    Default Re: room finish schedule

    Ok, I've tried playing around with it and can't seem to get it. How do I use these project parameters to identify the four walls as north/south/east/west? Thanks for the responses!

  5. #5
    All AUGI, all the time
    Join Date
    2006-10
    Location
    Arlington, Texas
    Posts
    596
    Login to Give a bone
    0

    Default Re: room finish schedule

    If you're trying to link those parameters to the actual walls, you're out of luck. Can't be done as far as I can tell. Right now there is no good (intelligent) way to do room finish schedules. Very annoying.

  6. #6
    Certifiable AUGI Addict Dimitri Harvalias's Avatar
    Join Date
    2015-12
    Location
    Vancouver, BC Canada
    Posts
    3,753
    Login to Give a bone
    0

    Default Re: room finish schedule

    Certain portions of this are not 'automatic' per se.
    The project parameters are added in the schedule, not as part of the wall, so Revit won't detect which walls are north or south and fill a value in accordingly.
    You create them from the properties dialogue of the schedule and then they are available as fields in the schedule which you can then fill out.
    If you want separate values for Base and Wall for each direction (N, E, S, W) you'll also have to create separate parameters for those i.e each of the fields you want fille dout needs to have its own parameter associated with it. Schedule keys and formulas can really speed up the process of filling out the sched and you can re-use the schedule format from one project to the next.
    Attached Images Attached Images
    Last edited by Dimitri Harvalias; 2007-03-28 at 06:18 PM.

  7. #7
    AUGI Addict iru69's Avatar
    Join Date
    2004-10
    Location
    usa
    Posts
    1,591
    Login to Give a bone
    0

    Default Re: room finish schedule

    I always find it helpful to deconstruct an example to see how it's put together.

    I've attached one I did a while back (I haven't used it recently, so I can't vouch for how well it's working or what I might do differently now)...
    Attached Files Attached Files

  8. #8
    Member
    Join Date
    2007-06
    Posts
    2
    Login to Give a bone
    0

    Smile Re: room finish schedule

    I just looked at this Room Schedule and not only do I think it's a great layout, but it's a very useful way to see how to set up parameters (to allow for 'subcategories'). thanks a bunch irusun; i'm still learning this program and this was extemely helpful.

  9. #9
    Member
    Join Date
    2007-07
    Posts
    7
    Login to Give a bone
    0

    Angry Re: room finish schedule

    I am an ADT user and am trying to learn this Revit progam. Its a very cumbersome an inneficient interface.
    How on earth do I extract the room finish schedule data to fill in the data for the N S E W portions of the walls. If ADT can do this certainly Revit can (that was sarcastic)
    Shouldn't Revit be able to tell that if the boundary of a room is a cleanroom panel, that the material to put in the NSEW fields is "CRP" or whatever I define it? Surely this program can do that?
    I read the entries above, and even opened the shcedule as well. Not sure how it works. Any suggestions? I am sure I am missing something here it cant be this complictaed, or maybe it is.
    Thanks guys in advance for your help,
    Peter

Similar Threads

  1. Room Finish Schedule
    By Andy.88917 in forum ACA General
    Replies: 3
    Last Post: 2009-11-27, 02:52 AM
  2. Room Finish Schedule
    By oskyaqui in forum Revit Architecture - General
    Replies: 2
    Last Post: 2008-11-17, 08:21 PM
  3. Room Finish Schedule Error
    By SJohnson-HSD in forum Revit Architecture - General
    Replies: 8
    Last Post: 2008-07-21, 07:33 PM
  4. Quick Room Finish Schedule by Room Type
    By SCShell in forum Revit Architecture - Tips & Tricks
    Replies: 2
    Last Post: 2005-11-08, 02:21 AM
  5. Room Finish Schedule
    By Michelle Gibson in forum Revit Architecture - General
    Replies: 6
    Last Post: 2005-07-20, 03:25 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •