I have a finish schedule with a column for floor, base, N/S/E/W walls, and ceiling. I'm also doing a finish key with a mark for each finish, and then the manufacturer, ID number, color, etc.
I was hoping there was a way I could fill in the schedule key with each of my finishes, like P-1, P-2, etc. for all my paints, VCT-1, VCT-2, etc. for all my floor tile selections, and so on; then switch over to my finish schedule and have each of the finish marks available in a pulldown box for each item.
So I created the finish key as a Schedule Key, and I named the key "Finish Mark". I'm adding rows and filling in the information for each finish.
Now the problem is that in my finish schedule, I can only put the Finish Mark field in the schedule once. But I really don't want to create separate Keys for floor finish, base, each direction of wall finish, and ceiling. I want the entire finish key to appear as a single schedule.
I suppose I can just go through my entire finish schedule and fill in everything, but that's going to take awhile. Any suggestions?