Hi everybody,
I am doing the material take-offs for one of our residential projects. One of the items client specifically asked for was the information about the roof soffits. All my soffits are placed, but it looks like there is no way to schedule them or even include them in the material take-off schedule. Is there any workaround to solve this problem, besides using ceilings? Thanks.

dgreen.49364
2009-06-23, 11:43 PM
If you used ceiling to create them, then it is ceilings you will need to schedule. You can name them in such a way and use filters to schedule only those roof soffits by themselves if that is what you are trying to do.