TanelF
2010-01-10, 12:32 AM
I modeled the shape of my building in the conceptual massing environment in Revit Arc 2010... added the the diamond patterning and a panels. I'm done in the concept massing environment and I loaded the mass into an actual project, however
1.) I don't have access to the diamond curtain wall anymore
2.) I would like to add a surrounding frame for my curtain wall but I can't access it
So my question is... what is the proper work flow for getting a conceptual mass into the project environment and have the capability to modify the curtain wall created in the conceptual massing environment ??
1.) I don't have access to the diamond curtain wall anymore
2.) I would like to add a surrounding frame for my curtain wall but I can't access it
So my question is... what is the proper work flow for getting a conceptual mass into the project environment and have the capability to modify the curtain wall created in the conceptual massing environment ??