alberto.malinverno
2010-02-19, 12:35 PM
Hi all,
i have a compuond floor with a 1/2" plaster below the concrete core structure.
But when i join the floor with the border concrete beam, or wall, the plaster passes trough them, even if the plaster layer priority is set to 5 (the lowest).
Furthermore, the concrete material takeoff is completely wrong: the beam volume is missing!
Everything works quite well if i remove the plaster layer below.
Is it a bug of revit 2010 or i am doing something wrong?
thanks...