PDA

View Full Version : Door Schedule



TerribleTim
2010-04-21, 10:32 PM
Hello again. Another issue I can't find an answer for. This time it's door schedules. Why can't I find an option to include the door number in my schedule? Where did they hide it? I added the door height, width, finish, frame material, etc. But I can't find the door number in the list. Any ideas?

cporter.207875
2010-04-21, 10:53 PM
Hello again. Another issue I can't find an answer for. This time it's door schedules. Why can't I find an option to include the door number in my schedule? Where did they hide it? I added the door height, width, finish, frame material, etc. But I can't find the door number in the list. Any ideas?

OOTB, Revit numbers doors according to their Mark parameter. Try adding Mark to your schedule and see if that works. If not, you will need to open the door tag and check it's label to see which parameter it reads.