PDA

View Full Version : Hyperlink Syntax in Schedule



phyllisr
2010-04-22, 02:37 PM
Does anyone know if there is a way to control the display of a hyperlink when it appears in a schedule? Ideally, I would like to use one short word rather than a lengthy path similar to what I can do in posts to the AUGI site.

Background

We use a Model Interaction Schedule on a Project Information sheet in all projects so our DA Staff and the team can track problems and issues and share information. Sometimes, it would be nice to have an image clarifying a problem that must be fixed instead of describing it in words. A hyperlink to the TEMP folder in the project directory is great but the lengthy path name makes the schedule larger than necessary.

Thanks in advance.