Is there a way to have the Schedule Key for Room Finish Schedule to show up in the Room Tag?

Alfredo Medina
2010-07-06, 08:41 PM
No, not in the the room tag. The only relation between the room and its finish key is in the room schedule. It would be good to have the ability to include the finish key and the ceiling height in a room tag, but so far this is not possible, at least not without manual input.