PDA

View Full Version : isolating worksets in a schedule?



twollifur
2011-09-21, 04:28 PM
We are working on a very large project with many other offices and have a workset dedicated to our office's portion of the work. We are trying to isolate our rooms in a schedule, but are unable to do so. Since workset is not a field in the room parameters I can't choose just our work. I even tried turning off all of the other worksets, but the other office's rooms still show up in the schedules.

Does anyone have any suggestions?

Thanks in advance,

Steve_Stafford
2011-09-21, 07:52 PM
You can create a new parameter for Rooms and filter by that value...add it to "your" rooms and filter so that only "your" rooms are included. A bit of work but it gives you the flexibility you want. You can hide that column in the schedule so nobody has to see it.