damon.sidel
2012-08-08, 03:55 PM
How do people deal with beams and floors in cast-in-place construction.
86566
As you can see, the beam and the floor intersect. I can join them and it cleans up correctly, but I have about a half dozen beams on each of 70 levels, so I'd be joining all day. Furthermore, we don't know the floor build-up yet, so I'd probably want to offset the beam below the floor finish.
So what do you do with cast-in-place construction and this detail? Thanks.
86566
As you can see, the beam and the floor intersect. I can join them and it cleans up correctly, but I have about a half dozen beams on each of 70 levels, so I'd be joining all day. Furthermore, we don't know the floor build-up yet, so I'd probably want to offset the beam below the floor finish.
So what do you do with cast-in-place construction and this detail? Thanks.