2013-01-29, 09:59 AM
Weird scenario (though I think this should not be "weird" at all, but rather as "normal" in the industry): We've done our door schedule and sent our RVT file out to an ironmongery specialist. He then worked on the model and added a schedule for ironmongery which he populated through instance and/or type parameters for the doors (some of which he added as Project Parameters).

Now I can probably incorporate those parameters quite easily (Transfer Project Standards), I can even copy-paste the schedule itself. So new parameters are no problem at all! But how would I get the actual data into our version of the model. And no I don't want to revert back (2 months worth of work) to the model we sent to him!

Some form of Excel copy-paste? Or do I need to somehow do some DBLinking? Or anyone come across this before?

DaveP
2013-01-29, 03:09 PM
There are several 3rd party programs available that can Import/Export between Excel and REvit.
Check the Autodesk Exchange:
http://apps.exchange.autodesk.com/RVT/List/Search?productline=RVT&query=excel&facet=&collection=
There are some cheap programs, some expensive, some powerful, some limited capability.
But there are quite a few to choose from.

irneb
2013-01-30, 05:07 AM
Thanks I'll have a glance at those, might even be my next RVt DotNet project :mrgreen:

antman
2013-01-30, 05:36 PM
I just like the term 'ironmonger'. .-)