tim_newsome
2013-11-12, 04:25 PM
I have a phased project. I have attached Existing.dwg & Phase-1.dwg to Phase-2.dwg and made them attachment style in hopes that I could simply attach Phase-2.dwg to all sheet.dwg(s) so layer managing to phase1 (fading) could be done once.
Now when I create new sheets and attach phase-2.dwg with attached (nested) Phase-1 and existing the two X-ref layers are coming in as they are in original files.
Is there a way for me to attach Phase-2 Base file with (2) X-refs attached to all 15 new sheet.dwgs and only layer manage Phase-1 & Existing ONCE?
Now when I create new sheets and attach phase-2.dwg with attached (nested) Phase-1 and existing the two X-ref layers are coming in as they are in original files.