Marcellus Ludivus Servus
2014-03-14, 08:23 PM
So I have searched the forum and haven't found an answer to this yet.
I created a Gross Area Floor plan to place areas. I have placed area boundary lines and placed areas with names.
I go to create a schedule using Area(Gross Building) as the category, I add the fields for name, area, area type, Level, etc... and click ok. I get a schedule with field headings but absolutely no areas scheduled. Anyone know why this would be happening? I am trying to get this done before the end of the day , finished my areas and tried to schedule and Bam! ->Fail. :(
I created a Gross Area Floor plan to place areas. I have placed area boundary lines and placed areas with names.
I go to create a schedule using Area(Gross Building) as the category, I add the fields for name, area, area type, Level, etc... and click ok. I get a schedule with field headings but absolutely no areas scheduled. Anyone know why this would be happening? I am trying to get this done before the end of the day , finished my areas and tried to schedule and Bam! ->Fail. :(