team member placed a plan detail callout an overall floor plan (A1x). Noted and dimensioned, hatching, etc. on a detail sheet (A5x). Typically we do plan detail callouts on the enlarged plans (A3x).
The question is, can the callout from A1x be relocated to the A3x WITHOUT creating a new callout from A3x, copying from the original detail A5x and pasting to a new detail?
been a few times where we EH (hide element in view) the callout and created a referenced callout (SIM).
Thanks.
Howard
The question is, can the callout from A1x be relocated to the A3x WITHOUT creating a new callout from A3x, copying from the original detail A5x and pasting to a new detail?
been a few times where we EH (hide element in view) the callout and created a referenced callout (SIM).