I'm working on a phased project, of which this is one of only a few that I've worked on despite my many years (14!) using Revit.

I have a nice "Interior Partition Types" schedule showing interior wall types created in the New Construction phase. There is one type (and one instance), "Generic - 5"", that is showing up that I traced to an infill of an existing wall. I demo'd a door in that wall and replaced it with a smaller door, so the infill is understandable.

However, I don't want the generic infill wall to show up in my schedule. Ideally, I would like to infill it with a different type. I also don't want to adjust the existing wall, because the existing conditions model was done as a scan, so I try to make as few modifications or adjustments based on assumptions as possible.

Thoughts?

PS - My 100% DD deadline is EOD Thursday, so I'd appreciate any ideas out there!

Revitaoist
2016-08-02, 07:35 PM
When all else fails, you can add a "appears in schedule" yes/no parameter and filter it by that.

damon.sidel
2016-08-04, 06:55 PM
Ah, a workaround! With a deadline in a few hours, I'll take it. Thanks!