View Full Version : 2015 door schedule and rooms



htlmv
2016-09-12, 05:26 PM
I had the doors associated with the rooms To and From but when I had to change the rooms from 1 phase to another, the To/From association is gone. any way to reassociate doors to rooms on the door schedule?

I do have the room calculations turned on in the door family.

htlmv
2016-09-12, 06:33 PM
OK...figured out that the door schedule is based on the phases but is there a way to show both phases on a singled schedule?

david_peterson
2016-09-13, 12:59 PM
You can chose the "Show All" in the phase filter.