Hi;
in an old thread talking about the occupancy load, there were a schedule for the IBC Code and the schedule has a parameter and it and this parameter was not in the Project Parameter as shown in the attached image.
1- How we can add a parameter to a schedule?
2- Where i can find this parameter if it is not shown in the project or shared parameter?

david_peterson
2017-05-31, 01:05 PM
If I had to take a guess, I'm looking at an image of a Key Schedule.
The Key Schedule is looking at the Parameter "Use Classification"
"Use Classification" was created in the shared parameter file and then added to the Project and I'm guessing applied to Room, Spaces, or Areas.
But that's just my guess.
ie you need to add it to your shared parameter file, I'm guessing it doesn't exist out of the box, in fact I'm sure of it. All of Autodesks Shared parameters are first letter upper case followed by lower case letters.

asiaashraf821339
2017-06-04, 08:03 AM
Thank you very much.
you were right it was a Key Schedule but the "Use Classification" parameter wasn't shared parameter, I've just named the Key schedule with Use Classification and it appears as the image.