i have building with basement, 1st floor and second floor. these are also my levels, plus in addition i have basement top plate level, 1st top plate level and 2nd top plate level. now when i create window schedule and set it to sort by level, i get group for each level plus i get group for 2nd top plate level, since there are some windows abovve this level. now how do i make the schedule list these windows under 2nd floor level instead of 2nd top plate level?

thanks

david_peterson
2018-01-31, 07:22 PM
The short answer is to associate them with that level. Just change it in the pull down.
The better option which I use all the time on large projects is to apply a number system whereby the first digit is associated with the level you want to schedule it by.
Then filter the schedule by window mark value begins with 1 for example.
I dislike using level to sort objects by since sometimes people copy and paste them incorrectly and then they either don't schedule or are on the wrong one.