we have linked models in our main model and we are scheduling the rooms from the linked models. in the schedule it references the level from said linked model i.e. level 1. we want it to schedule these rooms on the level they are on in the main model i.e. level 2,3,4,5.

Steve_Stafford
2019-12-11, 07:01 PM
I also replied at Adsk forum. Linked files will not recognize the host's levels for any elements that are in the link. The rooms will only report their own file's host levels. You can add RVT Project information to a room schedule to help identify which link they are related to. Alternately, put all the rooms in the host model and let the links provide the room bounding for them.