View Full Version : Door schedules
Brian F.
2003-12-17, 09:40 PM
I am doing a renovation and would like to keep doors not in the project scope off of my door schedule. However, even if I change the existing door property and move it to the "existing" phase, they are still included in my schedule. Am I missing a very easy step here?
gregcashen
2003-12-17, 09:47 PM
The step you are missing is to wait for 6.0 when schedule filtering will come into effect. Any day now...
beegee
2003-12-17, 09:52 PM
Brian,
The current 5.1 proceedure is to add a schedule parameter - call it "phase" , identify each door as New or Existing, group and sort the schedule using that parameter, hide that column in the schedule and then , on the sheet, split the schedule between those two groups and move the "existing" part of the schedule off the plotting area.
Allen Lacy
2003-12-17, 09:57 PM
Beegee, I think I know a simpler way. This is done by right-clicking on the door schedule in the project browser and changing the phase filter to show new doors only.
gregcashen
2003-12-17, 10:17 PM
Does that work? Doh! That's cool. Woulda helped last week. :?
Brian F.
2003-12-17, 11:18 PM
Once again, thank you everyone for your help!
Powered by vBulletin® Version 4.2.5 Copyright © 2024 vBulletin Solutions Inc. All rights reserved.