View Full Version : Revision Schedules - can I use alphabetical instead of numeral?



phindes
2005-06-14, 11:47 AM
Does anyone know if my revsion schedules can be scheduled as revisions "A" "B" "C" etc, instead of "1" "2" "3", which seems to be the default with revision clouds?

Thanks!

Paul

Shaun v Rooyen
2005-06-14, 02:19 PM
Nope! Wish we could though. Here we work with a,b,c for sketch design revisions, then 1,2,3 for CD'S.

archjake
2005-06-14, 07:28 PM
You can do it the "old school" way.

Create a generic annotation that is like the revision symbol. Place the symbol in your project. make the number a letter, and fill in the date & description. You may need to add those parameters to your annotation.

Then, Just create a note block for the revision symbol that includes the number, date, & description.