PDA

View Full Version : Another Scheduling question



bskripac
2006-01-26, 11:49 PM
If I have a schedule with wall type, their length, and unit cost how do I get a calculated value that is a length x cost total. I must be missing something when I try and do what seems logical I get and Inconsistent Unit error. Any insight or tutorials you could reference me to on scheduling?

Tom Dorner
2006-01-26, 11:52 PM
Try: Total Cost = Cost * (Length/1LF)

The secret is to eliminate the units of length so that your result is a number.

bskripac
2006-01-27, 01:36 AM
Thanks for the tip, that's perfect. Now I can apply that idea to some of the other calculations I will need to do. Makes perfect sense once somebody tells you about. Thanks Tom