View Full Version : Demo Schedule
Steve Jager
2006-05-18, 03:26 PM
Can you create a demolition schedule of removed items?
dhurtubise
2006-05-18, 03:55 PM
Sure, apply the same View Phase Filter to your schedule
Steve Jager
2006-05-18, 06:11 PM
All we get is everything and nothing. What type of schedule do you make? Do you have to create a schedule for each family type? We create a schedule as Phase Filter Previous + Demo, Phase New Construction. Does each of the families have to have some kind of parameter for this to work? Any help would be appreciated.
dhurtubise
2006-05-18, 06:28 PM
See the attach file, that should point you in the right direction
Steve Jager
2006-05-18, 07:05 PM
Thanks tons! I totally forgot about adding new phases under object settings
Thanks again.
dhurtubise
2006-05-18, 07:07 PM
Glad to help.