PDA

View Full Version : Can't schedule view numbers



Wes Macaulay
2006-07-17, 09:49 PM
In the interest of preventing a situation where multiple view numbers are on the same sheet (detail markers referencing to views with the same view number but on different pages), we'd like to create a view list schedule that shows the view number along with the view title, sheet, etc.

We don't want 1/A5.01 and 1/A5.06 and 1/A5.23 happening -- so we want to schedule the views so we can ensure that each detail view gets its own unique number. These details may come from sections, elevation or plan callouts, or drafting views. Using a custom view parameter, we can filter/isolate these views into a schedule.

All good -- except the view number isn't schedulable [sic]. Or so it seems. So we can't list all the views and quickly check to see if we've got duplicate view numbers. :banghead:

Anyone know how one could schedule the view number?