PDA

View Full Version : BUG: Level 1 doors in Level 2 schedule



rgesner
2006-09-01, 05:27 PM
See the attached ZIP file for the buggy RVT file.

The curtain wall and doors in this file were cut-and-pasted from a real project in which four doors on level 1 are showing up in the level 2 door schedule for no apparent reason. According to the schedule's level field and filter, they exist on level 2. Only these four doors were affected - all other doors do appear in the correct schedule.

The only strange bit of history is that at the time the doors and schedule were first created, the host curtain wall's Base Constraint was set to Level 2 and the Base Offset was set to negative 13'6, but changing the Base Constraint to Level 1 and the Base Offset to 0 didn't fix the problem.

Can anyone figure out why and how to fix it.

Thanks - Rusty

al
2006-09-05, 08:49 PM
I have the exact same problem. Did you find a resolution? Thanks.

dhurtubise
2006-09-06, 12:06 AM
Send it to support

Firmso
2006-09-06, 01:15 AM
Send it to support
Try just deleting the doors from the schedule and see what happens.
Replace with new doors if necessary and make sure they are on ground floor.

al
2006-09-06, 01:26 PM
I remade the panel that the door was sitting in -- removing the grid lines and then re-adding. Modifying the panel to a system one then back to a door did not work.