PDA

View Full Version : Door Schedule MYSTERY!!!!



Baldwin_4-6-0
2007-06-01, 03:22 PM
We had a Junior Designer recently start deleting door field parameters from the door schedule, instead of just hiding the columns.

This took every door single flush, double flush, existing, new & demo and combined them into one row on the schedule. if you right-click and pick "show" it shows all the doors in plan with all of them selected.

There is no filters & nothing is sorted or grouped

I cannot reverse this.

I've tried:
1. Changing door tag numbers, (this did nothing other than just change the number with no error but didn't fix schedule).
2. Changing the door number in the Row on the schedule (this just changes all of them & gives you the duplicate type mark error).
3. Removing all field parameters & then bringing them back again (nothing).

Anyone else have a rookie do this one?
Is there a fix?
Please help if you have had to fix this before.

bowlingbrad
2007-06-01, 03:29 PM
itemize every instance needs to be checked.

Baldwin_4-6-0
2007-06-01, 04:00 PM
yup I missed that