PDA

View Full Version : BUG - Grids in Linked Projects?



bowlingbrad
2007-07-30, 09:23 PM
I searched and didn't find a thread showing this so here it goes.

I'll try to make this easy to understand...

Project A has a plan view with some grid lines set to 2D extents.
Project A is linked into Project B and B's floor plan Link Visibility is set to "linked view"
Projet B has a plan callout that would still like to use "linked view" from overall floor plan.
If any grids are set to 2D in Project A, then the callout in B is screwed up.
The images below are from within Project B showing the problem with 2D grid extents.

I'm going to file a SR.