PDA

View Full Version : Equipment missing from schedule



sradley
2007-12-05, 07:10 PM
I have a multi-story building with equipment on all floors.
I have created a Master Equipment Schedule to keep track of all of the equipment.

For each plan sheet, I created another equipment schedule that shows the equipment on that plan.

It worked great until I had a pass-thru (#65) between two rooms.
The reference planes are set at the center of the family.
For some odd reason I can't get the equipment to associate with either room.
I have tried moving the planes to either side of the pass-thru with no luck.

Any suggestions?

Steve_Stafford
2007-12-05, 10:46 PM
Are the walls surrounding the pass through room bounding?

sradley
2007-12-06, 02:30 PM
Are the walls surrounding the pass through room bounding?

Yes. I know what you're getting at.
I could turn off the bounding for one of the walls and use wall separation lines to include the equipment.

I was wondering if the equipment could be associated with rooms, similar to doors.

Steve_Stafford
2007-12-06, 05:12 PM
I asked because I'm assuming that the pass through family IS associated with a "room", the space defined by the walls around it. I also assume that you didn't place a room there? If my assumptions are accurate then the pass through family isn't part of the other rooms because it isn't inside either of them.