neil.gordon
2008-01-09, 05:37 PM
I am currently finishing a project in Revit and wanted to show a exaple of my drawing packages to our group to help decide on settings for a project template. As I was getting the drawings together I noticed that the view references where not referencing the correct drawings from where they came. So what I wanted to know is there a way of updating these views after they have been created? As far as I can tell there is not I tried a number of different things but nothing seams to work. If there is not a way to update them is there a set process to make sure that the view is referencing the correct sheet when you create it? Any help would be much appriciated. I am using 2008 Revit Arch.