is it possible to split a schedule by level such that for example the doors for the 1st flr are on the one sheet and the doors for the 2nd floor are on another sheet?

Steve_Stafford
2004-08-25, 04:34 PM
is it possible to split a schedule by level such that for example the doors for the 1st flr are on the one sheet and the doors for the 2nd floor are on another sheet?Use a filter to limit the results to only doors on a specific level. Duplicate the schedule and change the name and filter value to the next floor. Then you can place each separate schedule as desired.

jwilhelm
2004-08-25, 05:24 PM
THANKS STEVE!