currently working on a project where we did a small addition to the rear of the home. have since started construction and they now want to do more work. the demo on the first floor is no longer needed. is there a way to get rid of it or at least keep it from showing. basically i want to use the current CD's as the new existing conditions. how do i do that?

Andre Carvalho
2008-06-16, 03:23 PM
You can select the wall that are set as demolished, go to its properties and set the phase demolished to None. They will be back to existing status.

Or, if you want to keep them as demolished but just don't want to show them as demolished, you'll have to play with the phase filters (like setting it to None, if it works for you).

Andre Carvalho

jeffh
2008-06-16, 05:00 PM
You should be able to do this by adding another phase to the project. Just add a phase after "new construction" rename new constructiuon to "phase 1" or something like that. Then work in the new phase. You should be able to show what you want that way.