pdavis
2008-12-17, 05:12 PM
We are running a combination of Max 9 and Max Design 2009 with Backburner 2007 running as a service on our render farm machine. We are using the "Week Schedule" feature within Backburner monitor to control when the render farm machine become available, however we are noticing that Backbirner Server Service still wants to consume 50% of a workstations processor time when it is not active. Has anyone else run into this and found a solution?
The majority of the render farm machines are desktop workstations that are used from 9 to 5. But in the evening we want to add those machines to the farm and this has proved to be very beneficial. However, Max needs to shut down when not in use and this is not happening.
Thanks.
The majority of the render farm machines are desktop workstations that are used from 9 to 5. But in the evening we want to add those machines to the farm and this has proved to be very beneficial. However, Max needs to shut down when not in use and this is not happening.