I prefer to split up my schedule information by floors but can't figure out how to place a gap or dummy row between floors on my room and door schedule. Any advice on how to achieve this?

saeborne
2009-01-02, 07:39 PM
In the schedule window, Right Click > View Properties > Sorting / Grouping > Edit...

This window is how you would sort the sequence of items in a schedule. For most schedules, you can sort by "Level," which should do the trick for you. If you can't sort by Level, then it's probably because you have to add "Level" as a field that the schedule.

There is also a check box called "Blank Line." Sounds like you want to check this box.


Hope this helps.