PDA

View Full Version : scheduling costs



johnf.77896
2009-01-15, 10:32 PM
I thought I saw a thread on scheduling costs but I cant seem to find it anymore. When you put in a cost in a wall or slab how does that get scheduled? Is it a total cost or can you do a lin/ft or sq/ft cost and have it calculate it? Any help would be greatly appreciated.

Thanks
John Fleming
GMK Architecture, inc.

dgreen.49364
2009-01-16, 12:17 AM
In the Fields section of the schedule you are going to create a Calculated value. Make sure the parameters you want are in the field, i.e. cost and area or volume, whichever, then create a calculated value, using a formula with those two parameters. It can be a little tricky using the right units and make sure you use * for multiplication and not x. I believe, also, that you have to check the Itemize every instance box in the Sorting/Grouping tab.

Hope that helps.

johnf.77896
2009-01-16, 05:40 PM
thanks for the reply. Where can you change the units in the default "length" instance parameter?

thanks
John Fleming
GMK Architecture, inc.

johnf.77896
2009-01-16, 06:15 PM
Never mind, figured it out. Need to use something other than the default in the schedule field format.