PDA

View Full Version : doors schedule doesn't update



gravelin
2004-10-19, 08:05 AM
In a doors schedule using "from room", "to room" fields, the schedule doesn't update if I flip the door. I need to DO IT MANUALLY ???
Not REVIT like...

beegee
2004-10-20, 03:39 AM
You're correct - it doesn't update. (... haven't seen that before )

Its looking like a bug to me. Everything else works dynamically - two way - in the schedule and this should too.

gravelin
2004-10-20, 06:08 AM
I think like you
that's a bug
I think Revit is great because we can modify what we need, where we want, when we want and all is updated...