How do you guys deal with grading the site for a building pad? And how do you deal with that in terms of "phasing". I have a site that we are building basically 3 different buildings spanning 3 different phases. What I did was modeled an existing conditions model as my "base plan". I then linked that into a model for phase 1 and created all of our phase 1 stuff there. Same thing for phase 2, linked in phase 1 and modeled all of phase 2 in that one, so on and so on.
Here's my dillema. I had to create a building pad in the base model for each new building. Even though I set the parameter of the building pad to the phase it will be created, I still can't figure out how to get the site plan to show correctly. It shows the ground with this huge cut in it where the phase 2 building pad would be, even though I'm looking at it for phase 1.
Any ideas? Am I going about this totally wrong? How do you do this?