We're working on a project in REVIT as are our mechanical, electrical and structural consultants. In the architectural model we have set the gridlines and levels. My question is, what is the proper practice for the consultants to use when it comes to the gridlines. Are they supposed to link our grids into their model or are they supposed to copy our grids to their model? The problem we have is that they copied our grids to their model and the structural have now moved grids and added grids to suit them, the architectural grids have adjusted as the floor plan has been modified and the MEP grids haven't updated with the architectrual grids so our project now has three sets of gridlines.